Approximate average peak-hour delay
The project context.
Architects United was working on an industrial and logistics park at Bhiwandi, with high vehicle movement expected due to e-commerce warehousing, staff movement, parking activity, and heavy vehicle operations.
The project required a clear understanding of traffic flow at the park entrance and internal lanes, especially during peak-hour conditions.
The site involved multiple movement zones, including the ESR Park, park entrance, parking area, and Amazon warehouse, creating complex origin-destination traffic movements.
There was a need to assess whether the proposed road and entrance configuration could handle peak-hour traffic without excessive congestion.
Heavy vehicles, buses, cars, two-wheelers, and cycles had to be considered using appropriate PCU factors and vehicle movement assumptions.
The project also required swept path validation for truck manoeuvring inside the park to ensure safe and practical vehicle movement.
Boom gate delays had to be evaluated because entry control could create queuing and congestion at the park entrance.